NEW QUESTION # 14
What are some of the key characteristics of the implementation approach in the SAP Activate methodology? Note: There are 2 correct answers to this question.

  • A. Scaled agile framework built in
  • B. Based on ready-to-use content
  • C. Fixed scope
  • D. Cloud ready

Answer: B,D


NEW QUESTION # 15
Working in an Agile approach, what should your planning look like at the beginning of the Realize phase?

  • A. Durations of all sprints for the full release defined based on planned complexity.
  • B. Project scope and planning are completed and final.
  • C. Scope and duration of testing is finalized.
  • D. User Stories are in Ready state for only the first 2 to 3 sprints.

Answer: D


NEW QUESTION # 16
Which of the following are included in ready-to-use content in SAP Activate? Note: There are 2 correct answers to this question.

  • A. SAP Best Practices
  • B. Business models from leading companies in each industry sector
  • C. Project accelerators
  • D. Baseline Activation Service

Answer: A,C


NEW QUESTION # 17
Which techniques should the SAP Activate practitioner follow? Note: There are 3 correct answers to this question.

  • A. Use agile approach throughout the project
  • B. Leverage dynamic extensibility and integrations
  • C. Optimize testing by running it only at the end of Realize phase
  • D. Reduce business user involvement for efficiency
  • E. Apply the fit-to-standard first mindset

Answer: A,B,E


NEW QUESTION # 18
Which of the following belong to the Application Design and Configuration workstream in the Explore phase? Note: There are 2 correct answers to this question.

  • A. Configuration definition
  • B. Change Impact Analysis
  • C. Integration prerequisites confirmation
  • D. Fit-to-standard workshop

Answer: A,D


NEW QUESTION # 19
Where do you activate SAP Best Practices from Cloud ALM to be used during the fit-to-standard workshops for SAP S/4HANA Cloud Public Edition?

  • A. Quality System
  • B. Development System
  • C. Production System
  • D. Starter System

Answer: D


NEW QUESTION # 20
When do you perform Quality Gate (Q-Gate) during a project? Note: There are 2 correct answers to this question.

  • A. At the end of Run phase
  • B. At the end of Discover phase
  • C. At the end of Realize phase
  • D. At the end of Prepare phase

Answer: C,D


NEW QUESTION # 21
What is an activity that is performed at the end of the Realize phase?

  • A. Load data into production system
  • B. Provision development system
  • C. Perform cutover simulation
  • D. Run the user acceptance test

Answer: A


NEW QUESTION # 22
When does the product owner accept or reject the user stories included in the Sprint?

  • A. During the daily Scrum meeting
  • B. During the Sprint Review
  • C. During the Quality Gate
  • D. During the user acceptance test

Answer: B


NEW QUESTION # 23
Which accelerators support the fit-to-standard workshop in the Explore phase? Note: There are 2 correct answers to this question.

  • A. Business Process Design Template
  • B. Test Strategy
  • C. Quality Gate Checklist
  • D. Backlog Template

Answer: A,D


NEW QUESTION # 24
What does a cutover involve? Note: There are 2 correct answers to this question.

  • A. Switching productive operations to new system
  • B. Aligning business and technical cutover plans
  • C. Completing solution end-user documentation
  • D. Presenting completed functionality to key users

Answer: A,B


NEW QUESTION # 25
What are the core capabilities in SAP Cloud ALM for operations? Note: There are 3 correct answers to this question.

  • A. Monitoring
  • B. License management
  • C. Event and alert management
  • D. Operation automation
  • E. Upgrade analysis

Answer: A,C,D


NEW QUESTION # 26
Which estimation technique can be used in an Agile delivery approach to size the User Stories during sprint planning?

  • A. Detailed bottom-up estimates that break each User Story into shorter tasks
  • B. Detailed top-down estimates by the Scrum Master in story points or Ideal Person Days
  • C. Relative estimates in Ideal Person Days that reflect the best estimates provided by the project team
  • D. Leveraging effort estimates for similar User Stories from another Scrum team

Answer: C


NEW QUESTION # 27
What are the SAP Cloud ALM Implementation capabilities? Note: There are 2 correct answers to this question.

  • A. Natively built in test automation
  • B. Perform implementation activities
  • C. Monitor project performance centrally
  • D. Check data quality prior to migration

Answer: A,B


NEW QUESTION # 28
Which of the following is part of the Explore phase for new implementations? Note: There are 2 correct answers to this question.

  • A. Data load preparation
  • B. Customer self-enablement
  • C. Fit-to-standard
  • D. Cutover plan

Answer: A,C


NEW QUESTION # 29
What are the capabilities of Task Management application in SAP Cloud ALM with SAP Activate methodology tasks? Note: There are 3 correct answers to this question.

  • A. Launch SAP Cloud ALM apps to perform SAP Activate task
  • B. Assign SAP Activate task to a team member
  • C. Change description of SAP Activate task
  • D. Delete SAP delivered SAP Activate tasks
  • E. Create sub-tasks to break down the SAP Activate task

Answer: A,B,E


NEW QUESTION # 30
......