NEW QUESTION # 39
Your customer wants to calculate Estimate to Complete (ETC) as the difference between Current Planned Cost and Actual Cost. In Progress Settings, which option would you use in conjunction with the ETC method to meet this requirement? (Choose the best answer.)
- A. Cost
- B. Remaining Plan
- C. Effort
- D. Manual Entry
Answer: A
Explanation:
Reference https://ppm-help.saas.hpe.com/en/9.42/Help/Content/UG/PjMUG/view_pj_cost_data_costtab.htm Below is an example of the Financial Summary view on the Cost tab of the Project Overview page.
NEW QUESTION # 40
Which three are part of using the Rapid Implementation for Project Financial Management Applications macro-enabled Microsoft Excel spreadsheet to enter setup data?
- A. Import Projects.
- B. File Import and Export.
- C. Prepare setup data.
- D. Upload setup data.
- E. Generate CSV files.
Answer: C,D,E
Explanation:
https://docs.oracle.com/applications/farel12/projectop_gs/OAPFM/OAPFM2264569.htm#OAPFM2159921 Configuring Rapid Implementation: Procedure Project application administrators can use the rapid implementation feature to set up the Project Financial Management offering. Use the Rapid Implementation for Project Financial Management Applications macro-enabled Microsoft Excel spreadsheet to enter setup data and generate the ProjectsWorkbook.zip. Upload this .zip file to the Setup and Maintenance work area. When the upload completes, the offering is configured based on the setup information that you provide.
Perform the following steps to configure rapid implementation for the Project Financial Management offering:
Prepare setup data.
Generate CSV files.
Upload setup data.
Correct errors, if any, and reload the data.
NEW QUESTION # 41
Your client is involved in automation control systems installation. Over the years, they have analyzed their total project spend on specific resource classes. They have identified that their cost spread distribution factor on a 10 spread point scale resembles:
0-4-10-11-14-13-10-4-0-0. Identify two ways to handle this kind of a spread on their budgets and forecasts. (Choose two)
- A. Use the predefined S-Curve spread with small deviations on the spread points.
- B. Use the predefined Bell Curve spread with small deviations on the spread points.
- C. Create a new spread curve or edit an existing spread curve to exactly match the spread points and attach to a project template.
- D. Create a new spread curve or edit an existing spread curve to exactly match the spread points and attach to the resource class.
Answer: B,D
NEW QUESTION # 42
Your organization wants to capture the project details for work order labor and equipment resource transactions as part of a project-driven supply chain solution.
Which expenditure type class is recommended for the expenditure types that need to be defined for these type of transactions?
- A. Usages
- B. Work In Process
- C. Supplier Invoice
- D. Inventory
Answer: C
NEW QUESTION # 43
Your organization has decided to enable the common accounting and project accounting periods option while defining business unit implementation options.
Where will you maintain the accounting period statuses if this option has been enabled?
- A. Project Costing
- B. Project Foundation
- C. Subledger Accounting
- D. General Ledger
Answer: B
NEW QUESTION # 44
Which three file-based data imports are available for use in Oracle Project Portfolio Management Cloud?
- A. Project Templates
- B. Project Tasks
- C. Project Budgets
- D. Project Billing Events
Answer: B,C,D
Explanation:
Ref: https://docs.oracle.com/en/cloud/saas/project-portfolio-management/19a/oefpp/toc.htm
NEW QUESTION # 45
Which three features are part of Oracle Fusion Functional Setup Manager?
- A. feature opt-in for a best fit configuration
- B. modifying an existing implementation project task list by selecting more functional areas when needed
- C. guided task list for end-to-end setup requirements
- D. updating an implementation project task list by changing the opt-in configuration to suit the latest requirements
- E. export and import services for setup data migration between environments
Answer: A,C,E
Explanation:
https://docs.oracle.com/en/cloud/saas/applications-common/r13-update17d/oafsm/applications-cloud-using-functional-setup-manager.pdf Functional Setup Manager offers the following:
* Standardized application configuration and setup experience
* Feature opt-in for a best fit configuration
* Flexible processes for managing setup:
◦ Setup by functional areas for an adopt-as-you-go approach
◦ Implementation projects to manage setup
◦ Upload file to enter setup data in bulk
* Guided task list for end-to-end setup requirements
* Export and import services for setup data migration between environments
* Comprehensive reporting on setup data
NEW QUESTION # 46
You are implementing Project Portfolio Management (PPM) for a professional services firm. The firm rents multiple buildings for its operations. At the end of each month, they review the rent expense for the month and want to allocate the rental cost to all the projects and tasks that are executed by associates in each of the buildings. The source amounts must be proportionally allocated to the tasks based on the raw costs of the tasks from the previous month. Considering that all these costs are in General Ledger, what three allocation setups should you complete in PPM? (Choose three.)
- A. Allocate rental costs once each accounting period by using the "full" allocation method.
- B. Allocate rental costs once each accounting period by using the "spread evenly" allocation method.
- C. Allocate to all eligible tasks and prorate the allocation by the total actual raw cost accrued for each task during the previous accounting period.
- D. Define allocation basis by using Actual Amounts with a period-to-date amount class.
- E. Define allocation basis by using Actual Amounts with a project-to-date amount class.
Answer: A,C,D
NEW QUESTION # 47
Where should you specify the Default Capitalized Interest Rate Schedule?
- A. Manage Project Plan Type page
- B. Manage Project Type page
- C. Manage Capitalized Interest Rate Schedules page
- D. Manage Capitalized Interest Rates page
- E. Manage Expenditure Type page
Answer: B
Explanation:
The Default Capitalized Interest Rate Schedule should be specified on the Manage Project Type page. This option allows you to select a capitalized interest rate schedule that will be used as the default for projects or tasks that use the project type. A capitalized interest rate schedule defines the interest rates and dates that are used to calculate the capitalized interest amount for a project or task. Reference: https://docs.oracle.com/en/cloud/saas/project-portfolio-management/20c/oapfm/manage-project-costs.html#OAPFM2356101
NEW QUESTION # 48
Which precedence order is used by the system for labor schedules to distribute payroll cost?
- A. Assignment > Assignment Element > Element
- B. Assignment > Element > Assignment Element
- C. Assignment Element > Element > Assignment
- D. Element > Assignment Element > Assignment
Answer: C
NEW QUESTION # 49
Which three tools are available for accessing REST APIs?
- A. Web Browser
- B. Oracle Transactional Business Intelligence
- C. Programming Language
- D. cURL
Answer: A,C,D
Explanation:
Ref: https://docs.oracle.com/en/cloud/saas/project-portfolio-management/18b/fapap/Use_cURL.html REST API = REpresentational State Transfer (REST) Application Programing Interface (API)
NEW QUESTION # 50
Which two privileges are assigned to the Project Plan Management duty in Security Reference Implementation? (Choose two.)
- A. Manage Project Plan Resource Assignment
- B. Transfer Project
- C. Allocate Project Expense
- D. View Project Progress
Answer: A,D
Explanation:
Ref: https://docs.oracle.com/en/cloud/saas/project-portfolio-management/19a/oapjm/index.html#_Toc468200732_1_12 Topic - Privileges - This table lists privileges granted to duties of the abstract role Project Management Duty.
Granted Role - Project Plan Management
Privilege - only A and C are listed
NEW QUESTION # 51
Your organization has been using project class categories and codes for reporting purposes and is set up at the project level. You recently defined a new project type, Capital-Contract, and created new class categories named Build, Operate, and Transfer (BOT) and Build, Transfer, and Maintain (BTM), with class codes of Yes/No. But on creation of a project, you are unable to associate these class categories and codes.
Identify two setups that are mandatory for these class categories and codes to be displayed. (Choose two.)
- A. Class codes should be associated with a related set code.
- B. Class categories should be assigned to project type.
- C. Class categories should be assigned to business unit.
- D. Class codes should be assigned to project unit.
Answer: A,B
Explanation:
Ref: https://docs.oracle.com/en/cloud/saas/project-portfolio-management/19a/oapfm/project-foundation-configuration-manage-project-types.html#OAPFM360164 Topic - Associating Project Types and Class Categories: Examples Project classifications group your projects according to categories and codes that you define. When you associate project classifications with project types, the classification is available for selection on projects with that project type.
Use any of the following methods to associate class categories with project types:
Add a classification to the project type definition
For each classification that you associate with the project type, you can enable the Assign to All Projects option to automatically add the classification to the project definition for all new projects with the project type. When this option is enabled, all projects with this project type must be assigned a class code for the class category.
Add a project type to the class category definition
Enable the Assign to all Project Types option on the class category definition
NEW QUESTION # 52
A project administrator is trying to assign a team member for a project but cannot find the person in the team member list on the Project Definition page. What is the reason for this problem? (Choose the best answer.)
- A. Project roles are not assigned in the project.
- B. The employee is not assigned with a supervisor.
- C. The employee is not assigned to the project-owning organization.
- D. The employee is not assigned to a department.
Answer: D
Explanation:
Ref: https://docs.oracle.com/en/cloud/saas/project-portfolio-management/19b/oapfm/project-foundation-configuration-define-project-resource-breakdown-structures.html#OAPFM180158_2 Why can't I find persons in the list of resources when I enter team members, planning resources, or person rate schedules?
You can't find persons in the list of resources when you enter team members, planning resources, or person rate schedules in the following situations:
The administrator didn't assign a department while creating users. Persons must have an active assignment and be assigned to a department in Oracle Fusion Human Capital Management before they can be added as team members or entered as resources on the planning resource breakdown structure or person rate schedule.
The resource isn't active in Oracle Fusion Human Capital Management because the current date is before the effective date of the resource. If you want to include persons who will start in the future, select the Include people with future-dated effective start dates option when you search for the person.
Persons assigned as project managers aren't active as of the project start date.
The assignment of the person is terminated, and an appropriate value isn't set for the number of days to display people with terminated assignments. You can set the profile value appropriately at the site profile level using the Specify Number of Days to Display People with Terminated Assignments task in the Setup and Maintenance work area.
NEW QUESTION # 53
Your business user has created a purchase order (PO) that has the following attributes:
Accrue at Receipt = Yes
Matching Option = 2 way
Receipt Close Tolerance = 100%
After approval, the PO is closed for receiving without creating a receipt. An AP invoice is created by matching to the PO. The user now runs Create Accounting for Receiving Transactions and then the "Import and Process Cost transactions" ESS (Enterprise Scheduler Service) job using the Transaction Source parameter as "Oracle Payables". The user notices that there is no cost transferred to the projects. Identify two reasons for this problem. (Choose two.)
- A. When you have an AP invoice that is matched against a PO with Accrue at Receipt set to Yes, cost is transferred to project by payables.
- B. When you have an AP invoice that is matched against a PO with Accrue at Receipt set to NO, cost is transferred to projects by receipt accounting.
- C. When you have an AP invoice that is matched against a PO with Accrue at Receipt set to YES, cost is transferred to projects by Cost Management and not by Payables.
- D. When you have an AP invoice that is matched against a PO with Accrue at Receipt set to Yes, cost is transferred to projects only if there are accounted receipt lines.
Answer: C,D
NEW QUESTION # 54
Your customer wants to generate accounting based on project information associated with the transaction for all subledger transactions. Identify three subledger applications for which the project source is available for deriving accounts when configuring subledger accounting. (Choose three.)
- A. Fixed Asset
- B. Purchasing
- C. Payables
- D. Receipt Accounting
Answer: B,C,D
Explanation:
Ref: https://docs.oracle.com/en/cloud/saas/project-portfolio-management/19b/oapfm/project-costing-configuration-define-project-costing-integrations.html#OAPFM3094605 Topic - Deriving Projects-Related Accounts
NEW QUESTION # 55
You have projects and tasks defined with transaction controls, which does not allow certain types of charges to the project. Your business needs to create invoices in AP with this project every period and hence would like to make the process easier by creating a distribution set. As you create the distribution set, you notice that these distribution set lines are not validated against the project transaction controls and you are allowed to save it without any validation errors. Identify the reason why the project transaction controls are not applied. (Choose the best answer.)
- A. There is no expenditure item date information available on the distribution set line.
- B. There is no expenditure organization information available on the distribution set line.
- C. The account code combination is not available on the distribution set line.
- D. There is no expenditure type information available on the distribution set line.
Answer: A
Explanation:
Ref: https://docs.oracle.com/en/cloud/saas/project-portfolio-management/18c/oapfm/project-costing-configuration-define-project-costing-integrations.html#OAPFM174886 How can I validate distribution sets for projects information?
Oracle Fusion Projects performs validations on Oracle Fusion Payables distribution sets for payables invoices at the time you create the actual distribution set lines. It validates the project and task number during the invoice validation.
Distribution sets are typically used on recurring transactions, and the associated project does not have transaction controls. When you create a distribution set in Oracle Fusion Payables, the distribution set line is not validated against the project transaction controls in Oracle Fusion Projects because you do not enter an expenditure item date, which is required for transaction control validation. The expenditure item date is not provided because you use the distribution sets for an indefinite period of time.
NEW QUESTION # 56
Which three setups can be configured by using Rapid Implementation for Project Financial Management Applications?
- A. Expenditure Types
- B. Project Class Categories
- C. Project Templates
- D. Work Type
- E. Project Types
Answer: A,C,E
Explanation:
Rapid Implementation for Project Financial Management Applications allows you to configure some common setups for project costing and billing using predefined templates and spreadsheets. Some of the setups that can be configured using Rapid Implementation are expenditure types, project templates, and project types. Work types and project class categories are not part of Rapid Implementation. Reference: https://docs.oracle.com/en/cloud/saas/project-portfolio-management/20c/oapfm/implement-project-financial-management-applications.html#OAPFM2355871
NEW QUESTION # 57
Your business user has created a purchase order (PO) that has the following attributes:
Accrue at Receipt = Yes
Matching Option = 2 way
Receipt Close Tolerance = 100%
After approval, the PO is closed for receiving without creating a receipt. An AP invoice is created by matching to the PO. The user now runs Create Accounting for Receiving Transactions and then the "Import and Process Cost transactions" ESS (Enterprise Scheduler Service) job using the Transaction Source parameter as "Oracle Payables". The user notices that there is no cost transferred to the projects. Identify two reasons for this problem. (Choose two.)
- A. When you have an AP invoice that is matched against a PO with Accrue at Receipt set to Yes, cost is transferred to project by payables.
- B. When you have an AP invoice that is matched against a PO with Accrue at Receipt set to NO, cost is transferred to projects by receipt accounting.
- C. When you have an AP invoice that is matched against a PO with Accrue at Receipt set to YES, cost is transferred to projects by Cost Management and not by Payables.
- D. When you have an AP invoice that is matched against a PO with Accrue at Receipt set to Yes, cost is transferred to projects only if there are accounted receipt lines.
Answer: C,D
Explanation:
When the Accrue at Receipt option is set to Yes on a PO, the cost of the items or services is accrued when they are received, not when they are invoiced. Therefore, the cost is transferred to projects by Cost Management and not by Payables. However, if the PO is closed for receiving without creating a receipt, there will be no accounted receipt lines and no cost will be transferred to projects. To transfer the cost to projects, you need to either create a receipt or reopen the PO for receiving. Reference: https://docs.oracle.com/en/cloud/saas/project-portfolio-management/20c/oapfm/manage-project-costs.html#OAPFM2355855
NEW QUESTION # 58
You want to export your project plan to Oracle Project Financial Management Cloud after initial scheduling is complete in Microsoft Projects. Identify three conditions that must be met for exporting milestone tasks. (Choose three.)
- A. only one labor resource assignment with 100 effort
- B. percent work complete values of 0 or 100 percent
- C. only one labor resource assignment with 0 effort
- D. lowest-level tasks set up with zero duration
- E. lowest-level tasks set up with non-zero duration
Answer: B,C,D
Explanation:
Ref: https://docs.oracle.com/en/cloud/saas/project-portfolio-management/19a/oapex/define-project-management-configuration.html#OAPEX1357147 Topic - Microsoft Project Prevalidation: Explained The following table describes Prevalidation rules for tasks and resource assignments.
Level
Rule
Lowest-level tasks
One labor and multiple expense resources are allowed for a lowest-level task. Remove other resources.
Summary tasks
Only one labor resource with zero allocation is allowed for a summary task. Remove all other resources.
Milestone tasks
No subtasks are allowed under milestone tasks. Milestones must be lowest-level tasks.
Milestone tasks
Milestone tasks must have zero duration.
Milestone tasks
Only one labor resource, with zero effort, is allowed for a milestone task. Remove all other resources.
When exporting milestone tasks, ensure that the tasks:
Are lowest-levels task with zero duration, that is, the same start and finish dates.
Have only one labor resource assignment with zero effort.
Have percent work complete values of 0 or 100 percent. Any other values are set to zero before export.
NEW QUESTION # 59
As part of maintaining (importing new employees that were added last week) project enterprise labor resources in your organization, you submit the Maintain Project Enterprise Labor Resources process to create and update resources based on changes in HCM. You define maintenance conditions on the Manage Project Enterprise Labor Resource page to process both employees and contingent workers. (Choose the best answer.)
- A. Jobs
- B. Person Type
- C. Pool Membership
- D. attributes that the project enterprise resources are assigned after creation
Answer: B
Explanation:
Reference https://docs.oracle.com/cloud/farel8/projectcs_gs/OAPEX/F1082603AN23E61.htm Manage Project Enterprise Labor Resource Maintenance Conditions Project Enterprise Labor Resources: How They Are Automatically Created and Maintained Run the Maintain Project Enterprise Labor Resources process to create resources, remove resource availability for staffing, and maintain the resource search index.
Settings That Affect the Maintain Project Enterprise Labor Resources Process Create and maintain project enterprise labor resources by defining a set of conditions that specify the employees and contingent workers in Oracle Fusion Human Capital Management (HCM) to create as resources in Oracle Fusion Project Portfolio Management. Define the resource attribute values, such as the resource calendar and primary project role, to assign to the new resources.
The following table lists the criteria that you define for selecting HCM persons to create as project enterprise labor resources.
Selection Criteria
Description
Person type
Select the HCM person type for the process to use as criteria when selecting HCM persons to create as resources. Available person types are employees, contingent workers, or both employees and contingent workers.
Option to select people based on job
Select this option for the process to create resources for HCM persons with specific jobs.
Caution If you do not select job criteria for this condition, the process will create resources for all eligible people based only on the person type.
Jobs
If you selected the option to select people based on job, then select the jobs for the process to use as HCM person selection criteria.
The following table lists the attributes for which you specify values to assign to resources that are created for the condition.
Resource Attribute
Description
Option to manage resource availability and staffing
Select this option for resource managers to manage the availability and project staffing of resources who are created based on the condition. Resources who are managed in Oracle Fusion Project Resource Management are eligible to fulfill project resource requests.
Calendar
Select the resource calendar for resources that are created based on the condition. The resource calendar defines the work schedule for project enterprise labor resources, and includes working days and hours and any exceptions, such as holidays.
Primary project role
Select the primary project role for resources that are created based on the condition. Project roles are maintained in Oracle Fusion Project Management.
Cost rate and currency
Enter the cost rate and currency for resources that are created based on the condition.
Bill rate and currency
Enter the bill rate and currency for resources that are created based on the condition.
NEW QUESTION # 60
You have four resources in your organization: P, Q, R, and S.
Resource P - Project or resource calendar is active.
Resource Q - Project resource request dates are within the project or resource calendar effective dates.
Resource R - Resource calendar is complex, it does not contain seven days, and it contains more than one pattern and shift.
Resource S - Number of working days within the requested date range is not zero on the project or resource calendar.
Identify the resource for whom Resource Availability Capacity Score will not be calculated. (Choose the best answer.)
- A. P
- B. R
- C. S
- D. Q
Answer: B
Explanation:
Ref: https://docs.oracle.com/en/cloud/saas/project-portfolio-management/19a/oapem/evaluate-and-assign-resources.html#OAPEM916359 Topic - Resource Available Capacity Score: How It's Calculated Calendars Used to Calculate Resource Available Capacity Scores How the Resource Available Capacity Score Is Calculated
NEW QUESTION # 61
Using Oracle Time and Labor, your client wants to put in a validation process that allows only a certain number of maximum hours an employee can charge in a day, and a minimum of hours he or she can report in a week.
What feature would you use to meet this requirement? (Choose the best answer.)
- A. project time validation rules
- B. time entry rules
- C. time calculation rules
- D. time audit rules
Answer: B
Explanation:
To put in a validation process that allows only a certain number of maximum hours an employee can charge in a day, and a minimum of hours he or she can report in a week, you need to use time entry rules. Time entry rules allow you to define the conditions and actions for validating time entries based on various attributes such as hours, dates, projects, tasks, etc. You can also specify the error messages and severity levels for the time entry rules. Reference: https://docs.oracle.com/en/cloud/saas/project-portfolio-management/20c/oapfm/manage-project-time-and-labor.html#OAPFM2355991
NEW QUESTION # 62
You have a small project for a period of five months. Your budget amount for each month is spread evenly and is $1000 per month. The first month actual expense is $800 and there is a commitment for $600. Now you generate a forecast at the beginning of the second month. Identify the monthly Estimate-To-Complete (ETC) amount that the application would calculate for the remaining four periods, when the ETC generation method includes commitments. (Choose the best answer.)
- A. 0
- B. 1
- C. 2
- D. 3
Answer: D
Explanation:
Budget 5,000 Actuals 800 Commitment 600
ETC = Budget - Actuals - Commitment
ETC = 5,000-800-600 = 3,600 Budget available for next 4 months = 3,600/4 = 900/month
NEW QUESTION # 63
......